Coastal Security Scheme (Phase-I)
The CSS Phase - I was implemented from 2005-2011 with an outlay of 646 Cr. Under the scheme, Coastal States/UTs were provided with 73 Coastal Police Stations, 97 Check Posts, 58 Outposts, 30 Barracks, 204 Interceptor Boats, 153 Jeeps and 312 Motor Cycles.
Coastal Security Scheme (Phase-II)
The CSS Phase-II was approved by the CCS for implementation w.e.f. 01.04.2011 to 31.03.2016 with an outlay of Rs. 131.43 Cr. The Scheme envisaged for provision of 131 CPS, IO Marine Police Operation Centres (MPOCs) for Islands, 60 jetties, 131 Four wheelers and 242 Two wheelers. The scheme was granted extension up to 31.03.2020 with the approval of the CCS. As on date, 120 CPS have been constructed, 37 jetties have been constructed/ upgraded and the entire allocation of four wheelers and two wheelers has been procured. 6 MPOCs have been constructed.

